On the basis of the agreement signed on March 21 of this year, “Saluda” LLC is implementing the Avani HPP power transmission line. At this stage, the 4180 meter section of the cable track is completed, as well as an installation works of 35 kV reinforced concrete and 110 kV metal masts foundations. The above mentioned cable track, based on the customer’s request underwent construction-engineering expertise guidance by Lasha Bibiluri and confirmed that works are actually performed in accordance with the project. Currently masts and wires installation works is underway the completion is scheduled in August of this year.